The plan for development and construction of Hiep Thanh Wind Power Plant from August 2018 to September 2021, specifically as follows:
· 03/2021: Completion of legal procedures & project implementation documents.
· 04/2021: Deploying construction and equipment installation.
· 03-06/2021: Completed the first turbine tower foundation.
· 04-07/2021: Completed the first wind turbine.
· 06/2021: Completing the transmission line
· 06-07/2021: Completing the underground cable route
· 06/2021: Completing the substation basic construction & technical installation.
· 07/2021: Receive electricity from EVN
· 07-08/2021: EVN conducts operational testing for wind towers
· 09/2021: Commercial operation
Progress of completing the project and putting it into use/operation: September 2021 after the completion of acceptance test and commercial operation.