The plan for development and construction of Hiep Thanh Wind Power Plant from August 2018 to September 2021, specifically as follows:

·       03/2021:         Completion of legal procedures & project implementation documents.

·       04/2021:         Deploying construction and equipment installation.

·       03-06/2021:    Completed the first turbine tower foundation.

·       04-07/2021:    Completed the first wind turbine.

·       06/2021:         Completing the transmission line

·       06-07/2021:    Completing the underground cable route

·       06/2021:         Completing the substation basic construction & technical installation.

·       07/2021:         Receive electricity from EVN

·       07-08/2021:    EVN conducts operational testing for wind towers

·       09/2021:         Commercial operation

Progress of completing the project and putting it into use/operation: September 2021 after the completion of acceptance test and commercial operation.